Menu
3 JA

Preventive maintenance

Plans generate work orders automatically by time, meter or condition

PM plans
PlanAsset / classTriggerFrequencyTask listEst. hoursNext dueActive
PM-P101A-01 P-101A Meter (run hours) Every 1,000 h Pump 1,000 h service (9 tasks) 6 8,000 h ≈ 4 days Yes
PM-P101A-03 P-101A Time Every 12 months Pump annual overhaul (24 tasks) 48 12 Mar 2027 Yes
PM-K201-02 K-201 Condition Vibration > 4.5 mm/s Compressor vibration investigation 8 Triggered 09 Sep Yes
PM-PSV-ALL Class: Safety valve Time Every 24 months PSV pop test & recertification 4 Rolling Yes
PM-GEN-01 Class: Diesel generator Meter Every 250 h Generator service 3 Rolling Yes
PM-WH-01 Class: Wellhead Time Every 6 months Wellhead integrity inspection 4 Rolling Yes

PM-P101A-01 · Pump 1,000 h service

Trigger Meter: run hours, every 1,000 h
Lead time Create WO 7 days before due
Assigned crew Mechanical, Obite
Priority 3 Planned

Tasks

  1. Isolate and lock out (permit ref.)
  2. Check coupling alignment
  3. Replace lube oil, 12 L ISO VG 68
  4. Inspect mechanical seal
  5. Vibration check DE / NDE

… 4 more

Parts & labour

  • Lube oil ISO VG 68 — 12 L
  • Gasket set — 1
  • Mechanical fitter ×2 — 6 h